Acting as Principle Contractor to Network Rail, Trackwork were awarded the contract to carry out W10 Re-gauging works to Sandy Lane & Radford Road, Coventry
The objective of the contract was to lower 1200yds of track in order to achieve W10 + 100 gauge clearance to over-bridges. The core works were undertaken during 2 No. x 54 hour OROR possessions.
The scope of work comprised of:
Pre & post survey work.
S&T disconnections, reconnections & testing.
Renewal of 1200yds of ballast and sleepers with formation treatment.
Design, installation, maintenance & removal of TSR’s.
Welding & Stressing.