Milestone Reached at Long Marston

Posted: May 12, 2025

Trackwork is pleased to announce the successful completion of the first phase of works at the Long Marston rail infrastructure site, delivered for our client, Porterbrook.

This significant milestone marks a major step forward in the transformation of the 135-acre site and showcases the scale and complexity of the project. This phase included:

  • 13,000m³ of excavationAerial Photograph of the Long Marston Site showing sidings

  • 6,000m of track installation

  • Installation of 20 switch & crossing units

  • Installation of 10 buffer stops

  • All meterials supplied and manufactured by Trackwork

This achievement is a testament to the dedication, expertise, and collaborative spirit of the entire Trackwork team, who worked tirelessly to deliver high-quality results under challenging conditions.

We extend our thanks to everyone involved in this phase of the project, and we look forward to continuing progress as we move into the next stage of development.